The Ghana Lattice Organization Restricted (GRIDCo) says just Accra and Winneba will encounter blackouts in the coming days following development chips away at its primary lines and at the principle Pokuase sub station.
This, as per the Head of Framework Activities of GRIDCo, Mr Imprint Baah is to permit the organization encourage some critical ventures to guarantee power supply unwavering quality in the More prominent Accra Area.
At a press preparation in Accra Thursday [April 1, 2021], Mr Baah said all together for the activities to be finished the project workers have mentioned for certain blackouts on the grounds that as they assemble they need to associate it to the current framework.
There have been blackouts in certain pieces of the country, which has prompted individuals asserting Ghana has gotten back to "Dumsor" and subsequently requiring a heap shedding plan for GRIDCo.
However, Mr Baah guaranteed that there is no cross country "Dumsor" coming.
Mr Baah said this at a press preparation on Thursday, April 1, 2021.
He referenced a portion of these activities as the Thousand years Advancement Authority (MiDA) supported Pokuase substation and Kasoa Mass Stockpile Point establishments and the French Improvement Organization (AFD) financed Tema - Accra transmission line support project.
He clarified that with the significant transmission line project from Tema to Accra and to Mallam, Tema is presently a significant age center point with in excess of 1,000 megawatts being produced at Tema, "so we need enormous bandwidth to bring that out".
"Pokuase is in the northern piece of Accra and Pokuase is presently going to be a center point, where the force that is being emptied from Aboadze on the 330 KV will currently come to Pokuase, prior to being shipped off Tema", he explained.
He added that "Pokuase will currently permit the ECG the adaptability to fulfill need in to northern piece of Accra and in the event that there are difficulties somewhere else in Accra, burden can without much of a stretch be moved to that territory. So Pokuase will improve supply unwavering quality here."
He further expressed that the interest for power is high in Kasoa, henceforth, a substation is being underlying Kasoa.
"Kasoa right now is being provided from Mallam and Winneba. Also, that is joined by a ton of blackouts thus much misfortune inside the conveyance organization. So Kasoa is being built and will be finished in August or September. Pokuase will be finished by June, July"
Every one of these undertakings as indicated by him, must be finished on time when there is an arranged blackout nearby.